How RAS Equipment Works Together: Check the Connections Between Treatment Stages

Drum filters, treatment tanks and connecting pipework in a YUTANK RAS facility

RAS equipment works as one system not because a drum filter, MBBR biofilter, degassing tower and oxygenation unit appear in a neat line, but because each stage receives water under conditions it can handle and passes that water on to the next stage as intended. Even if individual equipment specifications look suitable, poor coordination between piping, water levels, flow splits and maintenance arrangements can still create operating problems.

If you already have a RAS equipment list or process flow diagram, we would start by following the actual water paths. Where does the water go during normal operation? Where do the captured solids leave the system? And what changes when a unit is cleaned or taken offline? Those questions tell you more about how the system will operate than comparing equipment names in isolation.

What Does RAS Equipment Integration Actually Mean?

In a commercial recirculating aquaculture system (RAS), different equipment has different jobs. A drum filter captures suspended solids that can be separated mechanically. An MBBR biofilter supports biological nitrification, converting ammonia through nitrite to nitrate. Degassing equipment helps manage excess dissolved gases, while oxygenation equipment supplies oxygen required by the system. These processes support water quality together; they do not simply replace one another.

Knowing each unit's function is only the beginning. Equipment integration has three practical dimensions.

Treatment handoffs. What pollutants remain after an upstream process, and in what form and load will they reach the next stage? Uneaten feed and feces that are not removed promptly may continue to break down, adding to downstream oxygen demand and nitrogen loading. Mechanical filtration does not replace nitrification, and biological treatment does not replace the removal of captured solids.

Hydraulic handoffs. How much water actually moves through each stage? Is it gravity-fed or pumped? Can operating water levels, inlet and outlet connections, and pipe losses work together? A unit's rated treatment flow does not automatically become the flow it will receive after it is connected to a complete piping network.

Operational handoffs. During cleaning, sludge discharge, isolation or maintenance, which flow paths change? Which treatment functions may temporarily be reduced, and who is responsible for monitoring and responding? A normal-operation diagram cannot answer all the questions raised by maintenance conditions.

If you are still comparing equipment types and models, our RAS equipment overview and guide to selecting RAS equipment for a commercial fish farm cover those earlier decisions. Here, the question is more specific: once the equipment has been considered, what needs to be checked between the units?

Follow the Actual Water Paths, Not Just the Equipment List

A process diagram may show a row of boxes: culture tank, filtration, biofiltration, gas management and return to the tank. That is useful for explaining treatment functions. It is not a field piping drawing. Real projects may use different branches, process arrangements, water levels and control methods. Protein skimmers and UV units are not required in every RAS, either.

Aquaculture tanks and recirculating pipework during construction of a YUTANK RAS project
Aquaculture tanks and recirculating pipework during construction of a YUTANK RAS project.

We find it helpful to distinguish two kinds of flow path.

First, the water that is treated and returned to the culture tanks. Water leaving the tanks passes through whatever solids removal, biological treatment and gas-management stages the project actually uses, then returns according to the design. The aim is not to force every unit onto a single line. It is to establish what enters and leaves each treatment unit and how that unit relates to the main circulation loop.

Second, the solids and wastewater that should leave the recirculating loop. Concentrated tank-bottom waste, drum-filter backwash and waste streams from other treatment processes do not necessarily follow the same route as treated water returning to the fish. If the discharge route is unclear, capturing solids in a drum filter does not by itself mean those solids have been removed effectively from the farming system.

A useful water-path drawing should therefore distinguish recirculated water, wastewater and the routes affected by equipment maintenance. How that wastewater is collected, treated and discharged must also fit the site's facilities and applicable requirements. A simplified process diagram is not evidence that the discharge arrangements have been resolved.

What Is Handed Over Between Mechanical and Biological Treatment?

Mechanical filtration and biological treatment often work closely together, but they address different problems.

Take a rotary drum filter. It captures suspended particles, including uneaten feed and fish feces, that can be separated by its screen. Backwashing then directs the captured waste into a discharge route. The filtered water may still contain dissolved ammonia, fine particles and dissolved substances that the screen cannot remove. For the equipment-specific operating side, see our drum filter backwashing and maintenance guide.

An MBBR biofilter relies on microorganisms growing on moving media to convert ammonia first to nitrite and then to nitrate through nitrification. That process also depends on suitable dissolved oxygen, alkalinity, temperature, water movement and aeration. Clear-looking drum-filter effluent is not proof that the downstream biological treatment requirement has been met.

If biological water-quality readings become unstable, we would not begin by asking only whether both a drum filter and a biofilter were purchased. We would look at whether solids capture and discharge have changed, whether actual flow into the MBBR matches the design intent, whether backwash discharge affects the main loop, and whether aeration, media movement and water-quality monitoring remain appropriate.

Those questions require operating records and the actual layout. Connections, media arrangements and aeration systems also vary between MBBR models. Two units carrying similar nominal flow ratings should not be assumed to be matched without checking those conditions. For YUTANK's published product information, see the MBBR biofilter tank page.

How Do Degassing and Oxygenation Fit Into the Main Loop?

A RAS may include a degassing tower, oxygen supply equipment and a biofilter aeration system. They can all affect dissolved gases, but they should not be treated as interchangeable processes.

Fish and microorganisms consume oxygen and produce carbon dioxide (CO₂). Degassing primarily helps remove excess dissolved gases; oxygenation adds oxygen needed by the fish and relevant biological processes. Some aeration or gas-exchange equipment can influence both oxygen and CO₂, but that does not establish that one unit can meet both requirements under every operating condition.

Degassing and oxygenation equipment with connecting pipework in a RAS facility
Degassing and oxygenation equipment often work together in RAS to remove unwanted dissolved gases and supply oxygen to the water.

For example, after water passes through a degassing stage, we still need to know where it flows next, where oxygen is added, and what the dissolved oxygen conditions are before the return and inside the culture tanks. Likewise, aeration in an MBBR supports both media mixing and the biofilm's oxygen demand. Adequate dissolved oxygen in a culture tank does not automatically mean conditions inside the biofilter are suitable.

That is why we would review CO₂ management, culture-tank oxygen, MBBR aeration and their monitoring points separately, then relate them to the actual water path. The order of equipment, the way water moves between units and the control logic must be defined for the project, not inferred from a generic treatment diagram.

For more on why these are separate considerations, read why CO₂ removal matters in a recirculating aquaculture system.

Why Do Pumps, Water Levels and Piping Matter at Each Handoff?

Even when each treatment unit is suited to its intended function, water may not move through the full system at the expected flow rate.

The actual flow through a unit depends not only on its own specifications but also on upstream water levels, downstream backpressure, pipe length, local restrictions, valve settings and the pump's operating point. Where water moves by gravity, the available level difference and losses along the route need particular attention. Where it is pumped, comparing a pump's nameplate flow with a treatment unit's nominal capacity is not enough.

Suppose two suppliers provide a drum filter and an MBBR biofilter. Their connection sizes may appear compatible, but if their design operating levels or inlet and outlet elevations differ, the combined water path still needs review. Using equipment from one manufacturer does not, by itself, guarantee that the piping system is hydraulically matched either.

We would begin with three questions: where does the actual water flow come from and go to in normal operation; which units might be affected first when levels change; and whether pumps, valves and monitoring points can reveal those changes. Detailed hydraulic calculations and final equipment selection should then be undertaken by the responsible project designers using real site conditions.

That is why similar flow figures on an equipment list are not a substitute for checking operating conditions and interfaces.

What Changes During Cleaning, Isolation or a Unit Shutdown?

A RAS does not spend every hour in one steady operating condition. Drum filters need cleaning, pumps and sensors may need maintenance, and biological treatment and oxygen supply have their own operating constraints. The important question is: if one stage stops or changes operating mode, what happens to the downstream water supply and essential treatment functions?

YUTANK drum filter showing backwash spray nozzles and a separate waste outlet
Separate backwash waste outlet on a YUTANK drum filter.

With drum-filter backwashing, for example, the waste discharge route should be distinguished from the normal treated-water return. Whether the cleaning cycle changes water levels or downstream flow depends on the actual model and hydraulic arrangement. Automatic backwashing does not mean the rest of the system is unaffected under every maintenance condition.

For any unit that may need to be isolated manually, the design and operating team should establish what can be isolated, which routes and treatment functions are affected, what monitoring and alarms are available, what backup capacity exists, if any, and who can authorize a shutdown or restart. A bypass is not automatically a safe solution. Sending water around a treatment stage and back to the tanks may leave part of the intended treatment undone. Whether a bypass is permitted, how it is operated and for how long must come from the approved project design and site-specific safe operating procedures.

The point is not to ask farm staff to change valves or test shutdown scenarios based on an article. It is to consider maintenance routes, responsibilities and response conditions before operation. If an abnormal condition occurs, follow the site's established safety procedures rather than adjusting critical equipment based on general guidance.

A Practical RAS Equipment Handoff Review Matrix

The table below can help you review an early equipment list, process diagram or supplier interface schedule. It is a discussion framework—not a mandatory process sequence, a completed hydraulic design or an approved control scheme.

Handoff interface What should be clear upstream? What matters to the downstream stage? Who should confirm it, and using what evidence?
Culture-tank discharge → solids removal Whether normal drainage and concentrated waste discharge are separate; flow route and operating conditions Whether solids reach the intended filter or waste-discharge route Relevant designers and suppliers, using tank drainage drawings, process diagrams and operating conditions to confirm interface responsibilities
Mechanical filtration → MBBR biofilter Actual throughflow, residual solids and backwash discharge route Whether water flow and loading reaching the biofilter match the design intent Drum-filter and biofilter interfaces, actual flow and biofilter operating requirements, reviewed together by the responsible parties
Biological treatment → degassing / gas management Biofilter effluent route, dissolved oxygen conditions and CO₂-management needs Whether the degassing location and treated flow cover the water path requiring gas management Project gas-management design and actual measurement points; identify any separate branch explicitly
Oxygenation / return flow → culture tanks Oxygen-addition location, return path, controls and measurement points Whether oxygen requirements in the culture tanks and relevant treatment stages have been considered separately Design water path, dissolved oxygen monitoring and control arrangements, confirmed by the appropriate responsible parties
Cleaning, isolation and waste discharge Which units may stop and which flow or discharge routes may change Potential untreated return, lost treatment capacity or an undefined waste-discharge route Maintenance procedures, waste facilities, alarm/backup arrangements and clear operating authority

This matrix serves two purposes. When you are buying equipment, it helps identify gaps where specifications are complete but the connection conditions are not. At an operating farm, it helps separate a problem within one unit from a problem in the way units interact.

If a project involves the purchase of only one unit, the supplier should not automatically be assumed to be responsible for the whole-system design. Equally, an integrated-system proposal should clarify who is responsible for equipment, piping, controls, installation and operational handover. Those responsibilities must be defined in the actual contract and design documents, not by this article.

How Can You Review an Existing Layout With YUTANK?

To make the review approach more concrete, consider two hypothetical situations used only to illustrate the questions. Neither represents a YUTANK customer project or a documented equipment failure.

Scenario 1: The drum filter appears to operate normally, but flow into the biological treatment stage is unstable. We would not immediately conclude that either the filter or the biofilter is faulty. We would first compare operating water levels, actual flow routes, whether backwash discharge affects the main loop, and whether there are additional splits between the two stages. Only after those interfaces are understood can the next technical investigation be narrowed down.

Scenario 2: Water is degassed and oxygenated before returning to the culture tanks, yet tank dissolved oxygen still fluctuates. Rather than immediately increasing an equipment setting, we would review the actual return route, where oxygen is introduced, measurement locations in the culture tanks and treatment stages, and changes in operating conditions. Several factors could be involved; installing a unit alone does not establish its effectiveness under the observed conditions.

For a new project, an initial process flow diagram (PFD) or equipment layout sketch is a reasonable starting point for discussing inlet, outlet, discharge and maintenance routes. For an existing farm, the actual pipework, water levels and operating records may be more useful than redrawing an idealized process diagram. You do not need every detail resolved before the first discussion.

Depending on the project scope, YUTANK can discuss equipment configuration, interface requirements and system-integration questions with you. Final engineering design, equipment selection and operating procedures must still be confirmed against the real project conditions. If the overall project inputs are not yet clear, our guide to information needed before designing a commercial RAS offers a useful starting point.

Frequently Asked Questions

Can individually suitable RAS equipment still work poorly as a system?

Yes. The capacity and suitability of each individual unit are only part of the picture. Piping, water levels, flow splits, solids discharge and maintenance arrangements must also work together. Individual specifications cannot replace a system-level operating review.

Does every RAS need its equipment connected in the same order?

No. Solids removal, biological treatment, circulation and gas management are important functions, but the arrangement depends on the project. Protein skimmers and UV treatment are not mandatory in every RAS, and some functions may be placed on separate branches.

If I have a drum filter, do I still need an MBBR biofilter?

A drum filter and biological treatment primarily deal with different types of waste. A drum filter captures mechanically separable solids; an MBBR uses microorganisms to convert ammonia and nitrite through nitrification. The specific biological treatment process must be selected for the project's loads and water-quality targets. A drum filter does not replace all biological treatment requirements.

Can a degassing tower replace an oxygenation unit?

Not as a general rule. Degassing and oxygenation have different primary purposes. Some gas-exchange equipment can affect both, but whether it can meet the actual CO₂ and dissolved oxygen requirements depends on the equipment and operating conditions and must be evaluated separately.

Can I simply open a bypass when one unit needs maintenance?

Do not assume that is safe. A bypass may change downstream water quality and available treatment capacity. Whether one exists, and whether it may be used under particular conditions, must be determined by the approved design, monitoring provisions and site-specific safe operating procedures—not by a generic article.

Do I need completed construction drawings before discussing equipment integration?

No. An initial process diagram, equipment list or known water routes can help identify the interfaces that still need attention. Those materials are not usually enough to finalize pipe sizes, pump operating points, treatment capacity or construction details; those decisions require actual project design conditions.

References

  1. Southern Regional Aquaculture Center (SRAC), Ronald Malone, Recirculating Aquaculture Tank Production Systems: A Review of Current Design Practice, Publication No. 453, October 2013. https://agrilife.org/fisheries/files/2013/09/SRAC-Publication-No.-453-Recirculating-Aquaculture-Tank-Production-Systems-A-Review-of-Current-Design-Practice.pdf
  2. Agricultural Marketing Resource Center (AgMRC), Recirculating Aquaculture Systems, April 2025. https://www.agmrc.org/commodities-products/aquaculture/recirculating-aquaculture-systems

Discuss RAS Equipment Connections With YUTANK

If you are comparing two RAS equipment proposals, or you have equipment in place but are unsure how the stages connect, we can begin with the process diagram, equipment list or site arrangement you already have. We can discuss which treatment responsibilities, inlet and outlet interfaces, maintenance access and handoff conditions are worth clarifying first. You do not need a full set of engineering parameters for that first conversation.

Contact the YUTANK team to tell us about your farming project or existing equipment arrangement, and we can identify the next system-integration questions to resolve together.

Contact YUTANK

Talk to the YUTANK Team

Tell us about your question, project or equipment requirements. Our team will review your inquiry and contact you using the details provided.

Share what you know. We’ll work through the details together.

RAS Project Inquiry